The Craig-Mona Project involves the transmission capability of two interconnected 345 kV transmission lines. UAMPS owns a 15 percent interest in the first segment, running west from Craig, Colorado to the Bonanza Power Plant in northeast Utah. UAMPS holds an entitlement to 54 megawatts of capacity in the second segment from Bonanza to an interconnection at Mona, Utah.

Dates: 1990 April 18-1993 October 20